Reelmaster 7000Page 6 -- 4Axles, Planetaries and Brakes
Service and Repairs
Brake Assembly
1. Flange head screw (6 per planetary)
2. Splined brake shaft
3. Planetary assembly (2 used)
4. Front wheel assembly (2 used)
5. Lug nut (8 per wheel)
6. Retaining ring
7. Spring plate
8. Compression spring
9. Jam nut
10. LH Brake assembly
11. Flange head screw (4 per brake)
12. Hex plug
13. Piston motor (2 used)
14. Flat washer (2 per motor)
15. Cap screw (2 per motor)
16. O--ring
17. O--ring
18. RH brake assembly
19. Gasket
20. Brake cable (LH shown)
Figure 1
FRONT
RIGHT
75 to 85 ft--lb
(102 to 115 N--m)
85 to 100 ft--lb
(116 to 135 N--m)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
17
18
16
17
75 to 85 ft--lb
(102 to 115 N--m)
19
19
20
CAUTION
When changing attachments, tires or perform-
ingother service,use correct blocks,hoists and
jacks to raise and support machine. Make sure
machine is parked on a solid level surface such
as a concrete floor. Prior to raising machine, re-
move any attachments that may interfere with
the safe and proper raising of the machine. Al-
ways chock or block wheels. Use appropriate
jack stands to supportthe raised machine. If the
machine is not properly supported by jack
stands, the machine may move or fall, which
may result in personal injury.
Brake Assembly Removal (Fig. 1)
1. Park machine on a level surface and raise cutting
units to allow easier access to front brake assembly.
Stop engine, engage parking brake and remove key
from the ignition switch.
2. Drainoil fromplanetary wheeldrive/brake assembly.
3. Chockr ear wheels and jack up frontof machine (see
JackingInstructions inChapter 1 -- Safety).Supportma-
chine with appropriate jack stands.
4. Remove wheel assembly.