1 - 6
MELSEC-Q
1. OVERVIEW
1.2 Manual Makeup
This manual is made up of 11 chapters and appendices.
This manual assumes that SW
D5C-QD75P-E is used to perform steps from
positioning system checking to operation in the following procedure.
<Sequence of steps taken by the user up to positioning system operation>
Step 1: Install and wire the positioning system. Refer To
• Install and wire the PLC (such as the QCPU, QD75, I/O modules and intelligent function
modules), servo amplifiers, motors, external switches and other external devices.
QD75 User's
Manual
Step 2: Check the SW D5C-QD75P-E functions and learn the basic operations. Refer To
• Check the system with which SW D5C-QD75P-E can be used. Chapter 2
• Check the functions that can be performed by SW D5C-QD75P-E. Chapter 3
• Install SW D5C-QD75P-E in the peripheral device and start the program. Chapter 4
• Learn the SW D5C-QD75P-E screen makeup and basic operations. Chapter 5
Step 3: Start operation of SW D5C-QD75P-E. Refer To
• Create a project which will be the object of operation for SW D5C-QD75P-E. Chapter 6
Step 4: Check the connection and initial operation of the positioning system. Refer To
• Specify the QD75 to be accessed, ports where cables will be connected, and others.
• Check the QD75 types and I/O addresses of the stations connected.
• Check connection according to the signal states from the external devices.
• Check the alarms and warnings of the positioning module.
• Check that the servo motors are run by JOG operation.
Chapter 7