John Deere RG5500 Lawn Mower User Manual


 
8
Remove shipping straps and window protective
sheets.
ASSEMBLY INSTRUCTIONS
Remove the sides, front, and back of the crate.
Remove the plastic bag, shrink wrap and bubble
wrap. Remove the metal clips that secure the
grinder to the crate base. With a fork lift, raise the
grinder from the wood base and set it in its final
position. See FIG. 1 and 2.
THE UNIT WEIGHS
1200 LBS. [544 kg].
TO LIFT, USE POWER
EQUIPMENT.
POSITION BASE
The RG5500 Spin/Relief Grinder will require an operating area of about 119" W x 127" D x 90" H
(302 cm x 323cm x 229 cm). The machine operator will operate the unit from the front of the machine.
Position the base to allow sufficient operating room in front and to the rear of the machine. See FIG. 1
and 2.
The base should be placed on a relatively level concrete floor, with ample ceiling height to allow for the
installation of the unit. Do not place the unit across two concrete slab seams or across a large crack.
FIG. 1
FIG. 23
83" [211cm]
OPTIONAL BOOM
41" [104cm]
OPTIONAL
PLATFORM
LIFT SYS.
45"
[115cm]
71"
[181cm]
88
[224cm]
45"
[115cm]
41" [104cm]
OPTIONAL
PLATFORM LIFT
83"
[211cm]
Optional
Boom Kit
71"
[181cm]
70"
[178cm]
R36"
[914cm]
FIG. 2