Trane BCXC-SVX01B-EN Blower User Manual


 
14 BCXC-SVX01B-EN
Pre-Installation
1. Consider the unit weight. Reference the unit weight on the unit nameplate or in “Dimensions
and Weights,” p. 15.
2. Allow sufficient space for the recommended clearances, access panel removal, and
maintenance access. Refer to Figure 2, p. 13.
3. The installer must provide threaded suspension rods for ceiling mounted units. All units must
be installed level.
4. Coil piping and condensate drain requirements must be considered.
Allow room for proper ductwork and electrical connections. Support all piping and ductwork
independently of unit to prevent excess noise and vibration.
Skid Removal
The unit ships on skids that provide forklift locations from the front or rear. The skid allows easy
maneuverability of the unit during storage and transportation. Remove the skids before placing the
unit in its permanent location.
Remove the skids using a forklift or jack. Lift one end of the unit off of the skids. Vibration isolators
for external isolation are field supplied.
Pre-Installation Checklist
Complete the following checklist before beginning unit installation.
Verify the unit size and tagging with the unit nameplate.
Make certain the floor or foundation is level, solid, and sufficient to support the unit and
accessory weights. Refer to “Dimensions and Weights,” p. 15. Level or repair the floor before
positioning the unit if necessary.
Allow minimum recommended clearances for routine maintenance and service. Refer to unit
submittals for dimensions.
Allow one and one half fan diameters above the unit for the discharge ductwork.