4.0 Planning and Installation Checklist
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer
on page v of this document.
DOC012R02 AOC 15/50 User Manual Nov 2001
27
4.6 Electrical Planning Considerations
The local wiring inspector should review the design of the electrical installation before work
starts at the site. The following items should be considered in the design/installation of the
electrical system:
• Wire sizes, length and type as described in Appendix M
• Conduit type and size
• Service entrance hardware
• Revenue meter specifications
• Protective hardware required by the interfacing utility
• Distribution panel(s) with properly sized circuit protection
• Single phase power for control house lights and receptacles
• Step down transformer characteristics
• Control house interior wire ways
• Control house junction box(es)
• Multiple unit control for wind power stations
• Twist cable termination box
• Foundation/conduit interfaces
4.7 Installation Tools and Equipment
The installation of the AOC 15/50 requires specific tools and equipment (see Appendix I).
Below is a breakdown of steps to take or equipment to have on hand for the three main
installation phases.
For tower assembly:
• Tower manufacturer’s assembly drawings
• Checklist of tower parts, hardware and tools
• Torque specifications
• Tripod, bucket, backhoe or boom truck
• Personnel for lifting and assembly
• Anemometer boom and brackets
To prepare machine:
• If wind turbine generator was shipped in a crate, remove from crate
• Check components
• Open blade crate
For installation:
• Slings, ropes, buckets and tools
• Adequately trained personnel