AOC 15 Portable Generator User Manual


 
Appendix G-2 Turbine Installation QA Checklist
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this
document.
DOC012R02 AOC 15/50 User Manual Nov 2001
153
Tip Brake Installation
Check
Ensure tip brake slides into blade end without obstruction
Tip brake cables properly attached to connector points
Ensure installation of low-profile washers
Torque 5/16 mounting nuts to 11 ft/lbs
Torque 3/8" studs to 18 ft/lbs
Perform tip brake pull test
Assy by Q.A. Date
Installing Turbine
Check
Tower top bolts torqued to 600 ft/lbs
Confirm free yaw with yaw lock disengaged
Install twist cables into twist cable junction box
Install anemometer assembly at proscribed location on tower
Assy by Q.A. Date
QA approval signature
Date