ROUTING FEEDER & DISTRIBUTION LOOSE TUBING
When completed and before moving to the next cassette pod,
1. Install completed cassette pod on the rear door.
2. Route all loose tubing as planned and use cable ties liberally to secure tubing to lances on door and in cabinet.
3. After all feeder and distribution cabling and loose tubing has been installed, spliced, and routed, re-insert cable entrance dock,
tilt it up as shown in the following illustration, and then slip the feeder and distribution cable clamps into the slots. Use extra
clamps to fill out the slots containing only one cable.
4. Pivot the dock to the floor of the cabinet and re-install the chock bar. Push the chock bar against the cable clamps.
5. Secure the chock bar and close the rear door.