Section 1. Preparation and Siting
1-2
UT30 (10 meter tower) tower stations:
Install 3 to 10 meter level sensors (Section 4)
Raise tower (Section 2)
Install instrumentation enclosure (Section 3)
Install 0 to 3 meter level sensors (Section 4)
ET101 / ET106 ET Stations:
Place instrumentation enclosure low on the ET Tower (Section 3)
Install sensor option (Section 4)
Slide enclosure to top of tower and secure with correct orientation
(Section 3)
1.2 Tools Required
Tools required to install and maintain a weather station are listed below.
1.2.1 Tools for Tower Installation
All Towers
Shovel
Rake
Open end wrenches: 3/8", 7/16", ½", (2) 9/16"
Magnetic compass
6' Step ladder
CM6/CM10
Tape measure (12')
Level (12" to 24")
Small sledge hammer
Teflon tape or pipe dope
Allen hex wrench (5/64)
UT10
Tape measure (12' to 20')
Level (24" to 36")
Pick or digging bar
Claw Hammer
Materials for concrete form:
Hand saw
(4) 12" wood stakes
(1) 2"x 4"x 8' piece of lumber
(8) 8p double-head nails
(8) 16p double-head nails
Concrete trowels
(2) 1 to 1.5" thick x 24" boards to support base above forms (optional)
Concrete (0.4 cubic yards)