Baldor AE11 Portable Generator User Manual


 
3-12 Receiving & Installation MN2415
AE25 Electrical Connections Applies only to AE25 Enclosed Series Generators
Single Phase Power Connections
The generator has a 240V single phase AC output. These connections are made at the power
terminal box shown in Figure 3-9.
Figure 3-9 Single Phase Output Power Connections
AE25 with Enclosure (Natural Gas or LPG)
Load
GND
Customer
AC Output Connections
(to Transfer Switch)
L1
L2
N
L1 to N
L2 to N
L1 to L2
120VAC
120VAC
240VAC
Remote Start and Battery Charger Connections
Figure 3-10 shows the connections for the battery charger and the remote start contacts of the
transfer switch. When the Remote Start Switch is closed, the generator will start. The unit will
remain running until this connection is opened. When the Remote Start Switch is opened, the
control circuits allow the engine to run for approximately 6090 seconds before it shuts off. This
time delay allows the engine to run unloaded to cool down before stopping.
Figure 3-10 Remote Start & Battery Connections
Remote Start Switch
(Close to Start)
Customer Provided Optional Equipment
Battery
Charger
Out+
Out−
To 120VAC
(Shore Power)
Battery
+−
TB1
Twisted Pair Wire
16AWG
R1
R2
AE25 with Enclosure (Natural Gas or LPG)