Turbomachinery Package Specification Titan 250 Generator Set
16.2.6 Source Inspection
As an option, Solar can conduct a final product inspection at the supplier facility for the
following contract-specific items:
• Inlet system filter
• Inlet system silencer
• Exhaust system silencer
• Lube oil cooler
• Generator, including rotor balancing and standard generator testing
16.2.7 Customer Participation
As an option, the customer may witness specified tests on a noninterference basis and/or
hold point basis.
16.2.8 Weld Radiography
As an option, radiographic welding inspections can be performed on a percentage of the
gas fuel and/or lube oil system piping and manifolds.
© 2008 Solar Turbines Incorporated. All rights reserved. TPS250GS/908 - Preliminary