PRE-OPERATION INSPECTION
Pre-operation Inspection
o
Be sure that the operator's, safety and
responsibilities manuals are complete, legible
and in the storage container located on the
platform.
o
Be sure that all decals are in place and legible.
See Decals section.
o
Check for hydraulic oil leaks and proper oil level.
Add oil if needed. See Maintenance section.
o
Check for battery fluid leaks and proper fluid
level. Add distilled water if needed. See
Maintenance section.
o
Check for proper tire pressure. Add air if needed.
See Maintenance section.
Check the following components or areas for
damage, improperly installed or missing parts and
unauthorized modifications:
o Electrical components, wiring and electrical
cables
o Hydraulic power unit, hoses,
fittings, cylinders and manifolds
o Hydraulic tanks
o Drive and turntable motors and torque hubs
o Boom wear pads
o Tires and wheels
o Limit switches, alarms and horn
o Nuts, bolts and other fasteners
o Platform entry mid-rail/gate
o Beacon and alarms (if equipped)
Check entire machine for:
o Cracks in welds or structural components
o Dents or damage to machine
o
Be sure that all structural and other critical
components are present and all associated
fasteners and pins are in place and properly
tightened.
o
Be sure that both battery packs are in place and
properly connected.
o
After you complete your inspection, be sure that
all compartment covers are in place and
secured.