Multiquip GBP Landscape Lighting User Manual


 
PAGE 18 — GLOBUG LIGHTING SYSTEM • OPERATION AND PARTS MANUAL — REV. #0 (07/23/09)
SETUP
GBW/GBWE SETUP
Set the GBW on a fi rm level surface where there is 1.
enough space around the pentapod for the outriggers
to be deployed.
Remove the pentapod from the carrying case. The 2.
pentapod outriggers are secured together with a strap.
See Figure 6. Squeeze both tabs on the buckle to
unlock strap and release pentapod outriggers.
Releasing Pentapod BuckleFigure 6.
Lift mast up and deploy the pentapod as shown in 3.
Figure 7.
Deploying the PentapodFigure 7.
With pentapod fully deployed, hook the latch to lock 4.
the pentapod in place. The latch can be hooked in the
SQUEEZE
BUCKLE
PENTAPOD
OUTRIGGER
STRAP
DEPLOY
PENTAPOD
upper or lower position. Placing the lock in the upper
position will provide 1 foot (305 mm) more height. See
Figure 8.
Securing the PentapodFigure 8.
For the GBWE, attach the extension pole to the top of 5.
the mast as shown in Figure 9.
Attaching Extension Pole (GBWE)Figure 9.
To improve stability and prevent tipping of the lighting 6.
system, place sand bags on the outriggers or similar
weight on the weight hook as shown in Figure 10.
Sand Bags and WeightFigure 10.
UPPER
POSITION
LATCH
LOWER
POSITION
EXTENSION
POLE
BOLT
SANDBAG
WEIGHT HOOK
WEIGHT