Generac 1403-0 Spreader User Manual


 
Generac Portable Products Power Transfer System
6
11. If a two-pole circuit is not needed, the two-pole
coupled switch can be converted into two single-
pole circuits. Simply remove and discard the
handle tie connecting load management circuits
C and D, as shown on the right in Figure 8.
12. When steps 6 through 8 have been completed for
all desired circuits, install the WHITE (neutral) lead
coming from the Load Manager switch, as
follows:
a. Find an unused hole in the load center neutral
bar.
b. Trim and strip the white wire and install it into
the neutral bar.
c. Figure 9 shows a properly-connected WHITE
lead.
13. Install the GREEN lead coming from the Load
Manager switch, as follows:
a. Find an unused hole in the load center
GROUND bar.
b. Trim and strip the green wire and install it into
the GROUND bar.
c. Remove protective backing from the Attention
Decal. Per National Electric Code, affix decal
to load center surface closest to the green wire
installed in (b.) above.
d. If no ground bar exists, install the GREEN wire
into an unused hole in the neutral bar. Affix
label as described in (c.).
e. Figure 10 shows a properly-connected GREEN
lead.
14. Install the second Load Manager switch,
repeating the instructions given in Steps 4 through
13 above.
15. After both Load Manager switches have been
installed, install the load center cover. Set all
switches on both Load Manager switches to the
LINE position. Turn ON the load center MAIN
breaker. All breakers in the load center connected
to Load Manager circuits should be switched on.
Load Manager switch installation is now
complete.
Figure 10  GREEN Lead Installation
Figure 9  WHITE Lead Installation
(Neutral)
Figure 8  Convert Two Pole to Single Pole
Handle Tie Installed Handle Tie Removed