9
PN-51210 (Rev. 7/98)
A SSEMBLY
1. Remove the clevis assembly from the hydrostatic control cable end (see
figure 4). Remove one nut on the cable end. Insert the cable end into the
hole in the cable anchor weldment. Replace the nut and the clevis assembly.
2. Attach the clevis assembly to the center hole on the feed control lever.
3. Adjust the cable detent ball to contact the detents in the cable anchor
weldment when the control arm is in the forward position or reverse position.
Important! See hydrostatic pump start-up procedure.
1. Connect the PTO shaft female end to the rotor shaft using key stock and two
set screws contained in the owner's kit.
2. Connect the opposite end of the PTO shaft to the tractor.
3. Check all screws, bolts, and nuts for tightness. See torque chart, page 5 for
minimum tightening torque.
Nut
Clevis
Assembly
Detent
Ball
Feed Control
Lever
Cable Anchor
Weldment
Hydrostat
Control Cable
Insert cable
through hole
Figure 4
Connect the Hydrostatic Control Cable
(For models with factory installed hydraulic feed.)
Connect PTO Shaft