5. Preheat the engine
glow plugs
by turning the ignition
key (Figure 42) to the PRE-HEAT/RUN position. When
the preheat lamp (Figure 43) turns off, proceed
to step 6.
Figure 43. Pre-Heat Indicator Lamp
WARNING:WARNING:
WARNING:WARNING:
WARNING:
The engine's exhaust contains harmful
emissions.
ALWAYS have adequate
ventilation when operating
. Direct exhaust
away from nearby personnel.
DCA-45USI — GENERATOR START-UP PROCEDURE
Figure 39. Load Connections
NEVER!
manually start the engine with the
main, GFCI or auxiliary circuit breakers in
the ON (closed) position.
CAUTION:
1. Be sure and place the
main, G.F.C.I.
and
aux.
circuit
breakers (Figure 40) in the OFF position prior to starting
the engine.
Before Starting
Figure 38. Main, Aux. and GFCI
Circuit Breakers
2. Connect the load to the
Output Terminal Lugs
or
auxiliary
receptacles
as shown in Figure 39. These load
connection points can be found on the output terminal
panel.
3. Close all engine enclosure doors (Figure 40).
Figure 40. Engine Enclosure Doors
4. Place the voltage selector switch in the desired voltage
position (Figure 41).
Figure 41. Voltage Selector Switch
Figure 42. Ignition Switch