Servis-Rhino 2160 Brush Cutter User Manual


 
OPERATION
2160 02/10 Operation Section 4-14
© 2010 Alamo Group Inc.
OPERATION
FRAME ASSEMBLY
Inspect condition of mounting frame weldment.
Inspect condition of King Post frame.
Ensure all bolts and screws are in position and
are properly torqued.
Ensure all pins are in place and fastened with
screws.
Ensure frame is properly mounted to tractor
and hardware is propely installed and
tightened. OPS-B- 0021_E
BOOM ARM ASSEMBLY
Inspect condition of each arm section weldment
Ensure all pins are in place.
Ensure all bolts and screws are properly
installed.
Check condition of bushings at boom pivot
points.
Ensure each hydraulic cylinder is installed and
retained correctly. Ensure the proper size pins
are used to retain the cylinders in place and are
secured properly. OPS-B- 0022_I
Never attempt to lubricate, adjust, or remove material from the Implement while it is in
motion or while tractor engine is running.
(SG-20)