General
Before attempting the initial start of the generator set, be
sure it is serviced and ready for operation. Perform the
following:
Battery Connections
Refer to Battery Safety Section on page 11.
The battery cables are supplied with the generator set.
Service batteries, if necessary, as specified in the battery
section of this manual. Install battery. Connect battery
charger and jacket water heater if equipped.
Starting
After the installation is complete, make sure the lubricating
system is primed and the system is working properly.
Routine inspections are recommended.
Refer to the specified genset Operation manual for important
safety precautions and recommended procedures for starting
the genset. Only use the start-up procedures outlined in
the "Genset Operation Manual" when starting of the genset
is required.This is important to verify proper operation. Start
the genset as outlined in the operation manual and verify all
engine and generator display readings are accurate values.
PRE-START PREPARATION
z
Check ventilation and exhaust systems
z
Check all mechanical connections
z
Check the lubrication system for leaks
z
Check control configuration options
Ventilation
Verify all vents and ducts are open and free from any
obstructions. Verify dampers, if used, operate properly.
Exhaust System
Check the exhaust system for proper installation. Verify
there is at least 12 inches (305 mm) clearance between
exhaust pipes and combustible materials, all connections
are tight, and the exhaust will not disperse near doors,
windows, vents, or other openings.
Mechanical Checks
Check the generator set for loose or damaged components
and repair or replace as required.
Digital Control
Configure digital control as specified in digital control manual.
Electrical System
Verify all electrical connections are secure and wiring is
complete and inspected. Replace and secure any access
panels that may have been removed during installation.
NOTE
For genset inspection, start-up and
operational procedures, refer to the
MQ Power Operators manual for the
genset in use.
Make sure the Run/Off/Manual switch is in the OFF
position before connecting the battery cables. Failure to
do so will result in immediate starting of the genset when
connecting the generator set.