Effective April, 1999
IL 33-DB6-1
Page 12
F. Secure the PT Wires to the side of the left Trip
Unit Assembly Mounting Bracket, as shown,
using the existing hole and the (1) nylon wire
clamp, (1) .164-32 x .500" screw, (2) flat
washer, (1) lock washer, and (1) nut supplied.
Step 9: Installing the Sensors
A. Slide a Sensor over each bottom Breaker
Stab. The terminals of the Sensors should
face upwards.
For DBL-25 Fused Breakers Only.
Because of the location on the Fuse Tray, the
Sensors must be installed with the terminals
facing downward.
B. Reinstall the Finger Clusters removed in
Step 2A.
C. Slide the supplied the rubber grommet
(oblonged) onto the Sensor Harness to an
approximate position that will allow the Sensor
Harness to be routed along the front of the
Sensors.
D. Connect the Ring Terminals of the Sensor
Harness to the Sensors as shown. Refer to
Section 12 of the Retrofit Application Data,
supplied with the Retrofit Kit, for detailed wiring
specifications.
Sensor Style No.
8184A39H01 X1-X2 = 200 A
X2-X4 = 400 A
X1-X4 = 600 A