Scag Power Equipment GC-STC-V Brush Cutter User Manual


 
4
17. Using the weight support bar as a guide, identify
the four corresponding mounting holes, and the
existing hardware that will need to be removed in
order to secure the weight support bar to the
front of the machine as shown. See Figure 3-9.
18. Install one 7/16-14 x 1-3/4" hex head bolt into
each of the four mounting holes in the weight
support bar, and through the matching holes in
the caster support weldment. Secure this
assembly to the front of the machine using the
7/16- .5" x 1-1/4" x .083" flatwashers, and the
7/16-14 elastic stop nuts. Torque hardware to
59 ft. lbs. See Figure 3-9.
14. Attach the hood assembly to the machine by
installing the mounting post into the hopper
mounting brackets. Secure with the ring pins and
tighten the locking bolts. See Figure 3-8.
15. Install the hose from the blower assembly adapter
to the hopper hood and secure using the 6-1/2"
clamps.
16. Install the bag assemblies.
FIGURE 3-9
19. Operate and test.
FIGURE 3-8
Ring Pins
Ring Pins
Locking
Bolts
Locking
Bolts