Output voltage should be checked periodically to
ensure continued proper operation of the generating
plant and appliances. It can be checked with a
portable meter. Frequency can be checked by using
an electric clock with a sweep second hand. Timed
against a wrist watch or a stop watch the clock should
be correct within +/- 2 seconds per minute. All speed
setting adjustments should be done by a qualified
technician.
BEFORE STARTING
1. Make sure the generator is positioned on firm
l evel surface.
2. Check the crankcase for oil and maintain at a
proper level.
3. Check fuel level and fill tank 7/8 full with fresh
unleaded automotive gasoline. Never fill fuel tank
completely to the top. Always wipe up and remove
any spilled gasoline.
4. Make sure that the exhaust fumes are directed
away from people.
STARTING
1. Disconnect all loads to generator.
2. Turn gas line valve to ON position.
3. For cold engine, move choke lever to full choke
position For warm engine, move choke lever to half
choke or to RUN position.
4. Turn engine key switch located on engine to
start position.
5. When engine starts, let key return to the ON
position. Move choke lever to RUN position.
6. Loads may now be connected to generator.
STOPPING
1. Disconnect all loads to generator.
2. Turn engine key switch to OFF position.
3. Turn gas line valve to OFF position.
ENGINE CARE
Refer to your Kohler Owner’s Manual for proper
care and maintenance.
NOTE: When changing the oil on a hot engine, the
oil might overshoot the oil drain hole on the generator
base. Use a deflector (piece of cardboard or paper) to
direct the oil down the hole.
GENERATOR CARE
The generator head is a two pole, 3600 RPM, 60
Hz, brushless, revolving field and synchronous type
with one sealed radial roller bearing. The rotor of the
generator head is directly connected to the engine
crank shaft and the stator is rigidly coupled to the
engine casting via the generator head casting.
Exercising The Generator - The generator
should be operated every four weeks. Warm the
unit up by starting the engine and letting it run for 10 to
15 minutes. This will dry out any moisture that has
accumulated in the windings. If left, this moisture can
cause corrosion in the winding. Frequent operation of
the engine generator will also ensure that the set is
operating properly should it be needed in an
emergency.
Generator Maintenance - The generator head is
brushless and maintenance free. Any major generator
service including the installation or replacement of
parts should be performed only by a qualified electrical
service technician. USE ONLY FACTORY
APPROVED REPAIR PARTS. Obtain factory parts
from Customer Service at 1-800-270-0810.
A. Bearing - The bearing used in these generators
is a heavy duty sealed roller bearing. They require no
maintenance or lubrication.
B. Receptacles - Quality receptacles have been
utilized. If a receptacle should become cracked or
otherwise damaged, replace it. Using cracked or
damaged receptacles can be both dangerous to the
operator and destructive to the equipment.
WARNING, Stand-by Operation
If your generator is to be used as a standby
electric power source in case of utility failure, it must
be installed by a registered and licensed electrician
and in compliance with all applicable state and local
electrical codes. Also, local Fire Departments must be
consulted concerning proper and safe handling
procedures for gasoline. NEVER connect any
generator to any existing electrical system without an
isolating, UL approved transfer switch, installed by a
licensed electrician.