Column Placement
Reference your column placement chart for the particular villa you purchased. The center point measurements
will be described for your particular sized villa. Please locate these dimensions and mark them on your oor
or professionally laid slab. If your municipality requires a footing please see our recommendations for proper
column installation.
Anchoring the Main Support
Post
When scoring the concrete, make sure that the mark
is dark enough to see, as you will be drilling a hole in
the concrete. This hole will be where the anchoring
bolt is located. Also, it is the owner’s responsibility to
obtain a 1/2” masonry bit. This bit will be used to drill
the anchoring holes in the foundation. A masonry bit
may be bought at any local hardware store.
Refer to Figure 1 for steps 1 through 3.
Pre-drill the anchoring hole using a 1/2”masonry 1.
drill bit (see NOTE above). Drill the hole to a
depth of no less than 3”. Using a hammer, insert
the anchoring bolt by gently tapping the bolt
into place. Continue to tap into place until the
anchoring bolt is seated securely in the hole.
After drilling the hole and inserting the anchoring 2.
bolt, slide the main support post assembly on to
the anchoring bolt and tighten down using the
provided hardware.
Repeat these steps for all four corners of the 3.
villa.
Figure 1. Anchoring the main support post
Villa Assembly