381333-395 Operation 2-4
Figure 2-6. 7ACTS controls and indicators.
ACTS Electrical Operation
This procedure checks the electrical operation of the
automatic closed-transition transfer switch. See Figure
2-6.
Transfer Test
Both normal and emergency sources must be
available and the emergency source generator (if
used) must be capable of being started in this
procedure.
Perform the steps at the right. Observe the status
lights.
■ Black square means light is on.
□ White square means light is off.
** If you do not
want closed-transition transfer,
press the Closed Transition Bypass
pushbutton while the controller display shows
Waiting for In-Sync. This action causes open-
transition (momentary load interruption) transfer
to the opposite source, if conditions permit. Also
refer to the Group 5 Controller User’s Guide
381333-126.
1 The Transfer Switch Connected
to Normal and Normal Source
Accepted lights should be on.
2 Turn and hold the Transfer
Control switch clockwise to
Transfer Test until the engine
starts and runs (within 15 sec.).
The Emergency Source
Accepted light should come on.
3 The transfer switch will operate
to the Emergency position after
Feature 2B time delay. The
Transfer Switch Connected to
Emergency light should come on
and Load Connected to Normal
light goes off. You might see and
hear the brief overlap transfer.**
The transfer switch will operate
back to the Normal position after
Feature 3A time dely.
For immediate retransfer turn
the Transfer Control counter-
clockwise to Retransfer Delay
Bypass.
4
The Transfer Switch Connected to Normal light
should come on; the Transfer Switch Connected
to Emergency light should go off.
5 The engine-generator will stop
after the Feature 2E time delay
(unloaded running engine cool-
down). The Emergency Source
Accepted light should go off.