Woods Equipment BH80X Compact Loader User Manual


 
Operation 15
MAN0450 (10/28/2005)
Digging near center of swing so material may be
dumped on either side will produce good results. Never
dig near stabilizers.
Continue the trench by moving machine along trench
centerline away from existing excavation. Move
machine approximately one-half the effective backhoe
reach. Moving too far will require excessive down pres-
sure for digging and hand clean-up of trench bottom.
Figure 5. Trenching
SIDE SLOPE TRENCHING / EXCAVATING
Be careful when swinging loaded bucket on hill-
side. Always dump spoil on uphill side of backhoe
to minimize rollover possibility.
When operating on a side slope, the backhoe must be
positioned using one of these two methods as shown in
Figure 6 or Figure 7.
When operating on a side slope, always place the
trench spoil on the uphill side.
Figure 6. Level with Stabilizers
Cut a level pad for the uphill side of the machine and
place spoil on the downhill side as shown in Figure 7.
Figure 7. Level with Cut Out
TRANSPORTING
Always engage swing and boom transport locks
and attach Slow Moving Vehicle (SMV) sign before
transporting backhoe.
Power unit must be equipped with ROPS or
ROPS cab and seat belt. Keep seat belt securely
fastened. Falling off power unit can result in death
from being run over or crushed. Keep foldable
ROPS system in “locked up” position at all times.
Never leave equipment unattended with engine
running or with bucket in raised position. Always
engage swing and boom transport locks, relieve
system pressure by operating controls, and
remove ignition key before leaving equipment.
Transport and Swing Lock Installation
IMPORTANT
Before operating backhoe, disengage transport
lock bar and store swing lock pin. Push transport
lock bar down fully to prevent damage.
Engage transport lock by fully retracting boom and dip-
per. Position transport lock bar (1), located on right
side of swing frame, over transport lock pin (2). Secure
with safety pin (4). See Figure 8.
Center boom from side to side and install swing lock
pin (3) through swing frame and main frame. Secure
swing lock pin (3) with a safety pin (4) as shown.
During backhoe operation, store swing lock pin (3) in
the hole provided on the back side of the seat post.
Secure into position with safety pin (4).
Always raise stabilizers before transporting backhoe.