Walker Model MTLEFI Lawn Mower User Manual


 
Maintenance Instructions REPLACING/REPAIRING
83
Blade Overload Shear Bolts
NOTE: Shear bolts are not used on the DSD52 or
DSD62 mower deck.
The cutting blade is keyed to the blade hub by two
(2) shear bolts (10-24 x 5/8 in. stainless steel ma-
chine screws). These bolts are designed to shear
and protect the blade drive gearbox from damage if
the blade encounters a shock load.
Cutting Blade Shear Bolts
NOTE: Tightening the 5/8-18 blade mounting nut
to 60 ft-lb (81.3 N
·m) is also important for proper
shock load protection. It is important to not over-
tighten the mounting nut since this defeats (over-
rides) the function of the shear bolts.
If these bolts shear, remove the blade and install new
bolts. Refer to CHECKING/SERVICING in this sec-
tion for Sharpen Mower Blades which describes the
blade removal and installation procedure.
After reinstalling the blade, check blade timing by
moving blades through one (1) complete revolu-
tion. Make sure blade tips pass clear of each other.
If timing is incorrect, contact your Walker dealer.
PTO Shear Pin
The PTO drive shaft connection to the deck gearbox
has a shear pin to provide shock load protection to
the mower deck drive. This system provides prima-
ry shock protection in case of blade impact and will
normally shear before the individual shear bolts on
the blade hub.
When the PTO pin has sheared, use the following
procedure to replace it:
1. Loosen the two bolts securing the PTO shaft
guard on the deck; lift the guard off. (Holes in
guard are slotted for easy removal.)
2. Rotate U-joint on shaft to align the shear pin
hole with the hole (and shear pin fragment) in
the shaft. Use a punch to drive the remaining
portion of the old shear pin out.
3. Install new shear pin and secure with cotter pin.
PTO Shear Pin
IMPORTANT: Use only Walker P/N 8067-13
shear pins for replacement to provide proper
shock protection -- these pins are hardened to
shear under a specific amount of load.
4. Reinstall the PTO shaft guard.
NOTE: Use Walker P/N 8067-10 for heavy duty
gearboxes.
Before operating the deck, inspect the blade over-
load shear bolts and also check blade timing (on
gear driven decks) by moving blades through one
(1) complete revolution. Make sure blade tips
pass clear of each other. If timing is incorrect, con-
tact your Walker dealer.
Cutting Blade
Shear Bolts
Cotter Pin
U-Joint
Tube Assembly
Shear Pin
Split Spring Pin
(Retains U-Joint Held on Shaft
with Broken Shear Pin)
U-Joint
Shaft Assembly