15
OPERATION – STARTING
1. Conduct ‘Pre–start Procedures.
2. Switch the generator set to the applicable voltage setting.
3. Connect the load(s) to the circuit breaker.
WARNING: High voltage is present when the generator set is running.
4. Move the ‘Master Control Switch” to the appropriate position.
5. Adjust the voltage if necessary by turning the voltage adjustment knob located on the control panel.